Project Plan
January
- Vacate and take over 40/42 Ryecroft Street
- Disconnect gas/electric
- Obtain building regulation
- Instruct building contractor for demolition of 40/42 Ryecroft
Street and clear whole site, ready for handover to building contractor
and errect temporary fencing
Week 1 (4th February 2008)
- Take over site by builders and set up excavate for old drains,
divert and commission
- Excavate for new basement and build
- Order steelwork
Week 6
- Form all foundations for building and build to damp
Week 8
Week 10
Week 12
- Install floors and stairs
Week 13
Week 23
Week 27
- Brickwork and blockwork complete
Week 30
Week 32